********
At 8:00 this morning the guys showed up to put the wire and rebar in the foundation.
Right behind them was the pumper truck.
The operator got it unfolded to its full length. This slowed down traffic considerably on Little Elm.
Here's a close-up of his remote control gizmo.
Meanwhile the guys got all the wire in place and drilled into the old foundation to tie it to the new one with rebar.
The wooden box is the elevator pit.
As I said earlier, the holes in the block had to be filled to strengthen the walls first. Here they have poured the elevator slab and are starting on the block fill.
The pit being leveled and smoothed.
Finishing the block pour.
The back field has become a construction lot. The pour required two and a half truckloads of concrete mix.
The trucks were waiting their turn to be pumped.
Pouring the main foundation slab.
Beginning the smoothing process.
The builder-contractor, Jacob, pouring the footings for the gazebos...
and for the rest of the porch ..
and for the back deck.
Time to fold up the pumper arms!
The final smoothing by machine.
Jacob says he expects to begin framing in 2-3 days. It is moving right along now that the weather is good. I will post pictures every time there is enough change to warrant a new post.
********